A client asks whether the next round of negotiations will fit inside a $10,000 legal budget. The matter dashboard shows $6,000 billed. Before telling the client there is $4,000 to spend, ask the associate what work is already on the file and the partner what still has to happen before signature. Those two answers can change what you say on the call.
Read the budget on the same basis as the estimate
Clio describes the budget bar on its matter dashboard as comparing billed activities with the budget set in the matter’s billing preferences. Its budget calculation excludes tax. Work in progress has a separate definition and includes unbilled time on draft bills and bills pending approval. An entry appearing on a draft needs to be counted only once in your forecast. Clio’s matter dashboard guide
Read the engagement terms before assembling the figures. Is the client asking about fees through signing, or the total invoice including searches, filing fees and tax? If the agreed budget covers fees alone, extract the fee portion of the billed and unbilled records. Show any expected expenses separately so the client can see what payment to plan for. Also confirm whether the number discussed was an estimate, a cap, or an amount agreed for one phase.
Add the work already done and price what remains
Take a hypothetical hourly matter with a $10,000 fee budget through signing, excluding taxes and expenses. The firm has billed $6,000 in fees. The associate has another six hours recorded at $300 per hour, including two hours already on a draft bill. Those six hours add $1,800. The team has now performed $7,800 of work at the agreed rates.
For the remaining tasks, the associate expects four hours revising the agreement at $300 per hour. The partner expects three hours negotiating and reviewing the final documents at $500 per hour. That adds $2,700, bringing projected fees to $10,500. A dashboard reading of 60% billed sits alongside a forecast $500 above budget. The difference comes from the $1,800 already worked and the $2,700 still to come.
Ask which assumption the client can help resolve. Here it might be the number of negotiation calls. If the partner needs two hours instead of three, the forecast comes down to $10,000. Another two hours beyond the original three would bring it to $11,500. That gives the client something concrete to discuss before the next call is booked.
Choose a review point that leaves time to act
In Clio Manage, a firm can set a matter budget and select firm users for threshold notifications. Clio also lets individual users choose which matter notifications they receive. Give someone responsibility for the review and confirm their notification preferences. Choose a second trigger the team can recognize while doing the work, such as receiving the first marked-up agreement from the other side. Clio’s matter setup and notifications guide
Choose that trigger based on the next commitment. If sending the draft starts a negotiation round that could consume $2,700, ask for the forecast before sending it. Waiting for the next bill could leave the client deciding what to do about fees the team has already incurred.
Use a finished file to challenge the forecast
If the team is unsure about the three partner hours, use Matter Analytics in Keeney Analytics to locate a comparable closed matter and inspect its recorded hours. Return to the underlying entries in Clio to see which activities fell between the first markup and signing. Ask the lawyer what was different about that negotiation. A single partner call with both decision makers present may explain why that file finished sooner. Review comparable closed matters
Date the forecast and record who owns the next decision. A client update can give the fees incurred, the expected range for the remaining work and the assumption most likely to change it. If the other side introduces a new issue, revisit that assumption with the client while there is still a choice about scope, staffing or timing. Review the scope of the work